Quick answer: As of November 2026, the Spring Hill sewer moratorium is still in force. TDEC's consent order, accepted by the city on August 5, 2025, stopped new sewer connections for projects without vested sewer rights, and Ordinance 25-29 allocated all of the plant's remaining capacity on January 5, 2026. The city's fix is a $12 million sewer line to Columbia's system. On roads, the Buckner Road interchange is open, the Buckner Lane widening is projected to finish in December 2026, and US 31 widening is in TDOT's 10-year plan.
If you're shopping new construction in Spring Hill right now, ask about sewer before you ask about floor plans. A lot can have roads, pipes and a sign out front and still be waiting on capacity the city doesn't have yet.
I live just north of Spring Hill in Canterbury, in Thompson's Station, and I've been in real estate since 2013 with more than 500 transactions behind me. Reading the city's ordinances and project pages before an offer is part of how I work. Here's what Spring Hill has on paper, as of November 2026.
If you'd like me to look at a specific address, DM me, or text or call 615-392-1186.
What county is Spring Hill, TN in?
Spring Hill sits in two counties, Maury and Williamson. The city covers 26.442 square miles, about 12 miles north of downtown Columbia and 13 miles south of downtown Franklin. The county line runs through town, so two homes a few minutes apart can carry different county property tax bills. The city's own tax page lists separate payment portals for each county. For which neighborhoods sit on which side, see my Spring Hill neighborhoods by county guide. Most of the city's planning documents don't say which county a project is in. Where a source does, I say so below. Where it doesn't, I check by address.
What is the Spring Hill sewer moratorium?
On August 5, 2025, the Board of Mayor and Aldermen accepted a consent order from the Tennessee Department of Environment and Conservation (TDEC), Case WPC25-0093. The city's notice that day says Spring Hill self-reported 29 effluent exceedance violations to TDEC between 2023 and 2025. The order carries a $65,700 civil penalty.
The plant at the center of it is the city's Water Reclamation Facility at 3893 Mahlon Moore Road, in Maury County. The city describes it as a 5 million gallon per day plant with more than 150 miles of sewer lines behind it.
The order put a moratorium on new sewer connections for every project that doesn't have vested sewer rights under Tennessee law. It also suspended new sewer capacity availability letters, with an exemption for critical infrastructure. New projects that would otherwise go forward by right can proceed only if they use an alternative treatment system that adds nothing to the city's plant.
In October 2025 the board also paused reviews. Resolution 25-238, passed October 6, 2025, temporarily stopped accepting and approving construction plans, grading permits and building permits, citing a surge in project reviews.
Ordinance 25-29 assigned the rest of the capacity
On January 5, 2026, the board passed Ordinance 25-29 on second reading, 8 to 0 with one abstention. It took what was left at the plant and assigned it, project by project.
Projects with development agreements, Group 1, needed 207,403 gallons per day. Permit-ready vacant lots, Group 2, needed 62,500. The ordinance says the two groups together consume "the entirety" of the city's remaining treatment capacity, and it says it plainly: "No additional development capacity remains available at this time."
On top of those two groups, the ordinance set aside 65,000 gallons per day for critical infrastructure (a hospital on Reserve Boulevard and the city's Public Works and Fleet buildings), 365,000 for every building permit already active, and a 100,000 gallon per day reserve the board may use for nonresidential tenant improvements in existing buildings.
Group 1, projects with development agreements:
| Project or builder | Gallons per day |
|---|---|
| Legacy Pointe | 62,995 |
| June Lake | 58,000 |
| Spring Hill Commerce Center | 20,000 |
| John Maher Builders | 18,000 |
| Belle Springs | 12,600 |
| Barton Hills | 12,000 |
| Spring Hill Towne Crossing | 10,808 |
| Goodall Homes | 6,000 |
| Patterson Company | 6,000 |
| Smyrna Ready Mix | 1,000 |
| Arbor Valley | Shared among its builders, no figure listed |
Group 2 covers 250 permit-ready lots at 62,500 gallons per day. Named ones include Harvest Point (16,500), Brandon Woods (39 units, 9,750), Alaina Park (24 units, 6,000), Hardins Landing (24 units, 6,000) and Bluebird Hollow (22 units, 5,500).
Everyone else waits. Under the ordinance, a project that needs sewer can be accepted only if it has an allocation, uses no more flow than the property already did, or uses its own decentralized treatment system. Projects without one of those "remain ineligible for application acceptance or approval until new wastewater capacity becomes available or a future ordinance authorizes additional allocations."
The ordinance also polices the allocations it handed out. Every project with one must install a flow meter before it gets a certificate of occupancy. If a tenant goes over its allocation and doesn't fix it within five business days, the city will disconnect water service, and a third overage can mean a revoked certificate of occupancy. Those rules are written for projects with allocations.
An allocation for a neighborhood doesn't always cover every lot in it. On the November 16, 2026 board agenda, a 75-lot section at June Lake (inside Spring Hill, on the Williamson County side) had sewer capacity allocated for only 14 lots. The developer could finish its on-site pipes and plat all 75 lots at its own risk, but no sewer connection would be allowed for the other 61 until capacity is allocated. A first phase at Windfall, also at June Lake, had no capacity allocated at all and would build its infrastructure at the developer's own risk. As of November 28, the result of that vote hadn't been posted.
When does the Spring Hill sewer moratorium end?
The state decides when this ends. Under the consent order, the moratorium stays in place until the city "has not reported a bypass for a period of twelve consecutive months or an SSO of greater than 400 gallons for a period of twelve consecutive months and the Division has either rescinded or modified the moratorium in writing." An SSO is a sanitary sewer overflow, and the Division is TDEC's Division of Water Resources. The order also lets TDEC modify the moratorium to grant relief flow if the city shows less infiltration and inflow in its pipes or more treatment capacity. The city's own notices describe it as twelve consecutive months of meeting the order's performance standards. The order's words are the ones that count.
As of November 2026 I haven't found a notice that the moratorium has been lifted, and Ordinance 25-29 stays in force until new capacity comes online or the board replaces it.
What is the sewer line from Spring Hill to Columbia?
The nearest relief runs south. On October 19, 2026, the board unanimously passed Resolution 26-302 to move ahead with an interlocal wastewater agreement with the City of Columbia, whose council voted for it on October 8.
The plan is a 12-inch sewer main from Spring Hill's plant on Mahlon Moore Road to Columbia's system on the north side of Columbia's city limits. The project is about $12 million: $9 million for the pipeline and $3 million for upgrades to the Carter's Creek Pike Pump Station. Columbia would take a minimum of 500,000 gallons a day and a maximum of 1.5 million.
Spring Hill's announcement gives no start date. Columbia's own October 13 item says service begins only after Columbia's new treatment plant and the pump station work are finished, and it puts that plant's completion in 2027. Columbia projects Spring Hill's payments at $21 million to $62 million over 10 years, depending on volume.
Water: the Duck River limit
Water has its own limit. In the city's words, Spring Hill "pulls water from and discharges water into the highly protected Duck River," and as the city "brushes up against the limits for intake and outflow," it has to stretch the water it's allowed to draw.
Its answer is the Advanced Purification Project. Treated wastewater goes through advanced purification and on to a reservoir, where it's blended with raw water from the Duck River, and the blended water is fed back into the city's water treatment plant. TDEC approved a pilot on August 27, 2024, and the city called it the first project of its kind in Tennessee, with pilot construction expected in 2025. I haven't confirmed the pilot is running yet.
The project needs a reservoir. In early 2025 the board approved buying 111 acres next to I-65 near Brandon Woods (Resolution 25-68) for $8,093,385, about $73,000 an acre, paid in cash from the Sewer Development Fees Fund. A developer had proposed a subdivision there called Stone Creek, with more than 1,000 housing units. The city says the planned reservoir will sit on that land.
Storage went up this fall. The Southside Water Tank, just south of the Stonegate subdivision, came online in October 2026 with 2 million gallons, bringing the city to 12 million gallons of storage.
Outdoor watering runs on a schedule every May through September. Even-numbered addresses water on Sundays, Tuesdays and Thursdays, odd-numbered addresses on Mondays, Wednesdays and Saturdays, and nobody waters on Fridays.
Water and sewer bills went up in 2026
The city's base water charge and volume charge both went up about 30% for the year starting July 1, 2026, with the first higher bill in August. Sewer went up the same way. After this year, rates rise each year by whichever is greater, 3% or the increase in the Consumer Price Index. Stormwater went to $8.00 for most homes.
Utility rates here are the City of Spring Hill's published figures from its May 29, 2026 notice and are for planning only. They can change. Confirm current charges with Spring Hill Water before you rely on a number.
Roads: the Buckner Road interchange is open
Spring Hill got its second way onto I-65 on May 31, 2024, when the interchange at Buckner Road opened. Before that, the only I-65 access was the Saturn Parkway exit. It's a diverging diamond interchange, and the city says it paid $30 million of the $56.8 million cost, shared with TDOT.
The city ties the interchange to June Lake, and its planned totals there are large: 3.9 million square feet of office space, 1.3 million square feet of retail and restaurants, 2,900 homes and 400 hotel rooms. Those are plans, not buildings.
Buckner Lane widening
Buckner Lane is going from two lanes to five, two each way with a center turn lane. The North Segment, built by Jones Bros. under a $17,786,559.15 contract that started in 2023, is finished; the board approved its final change order on August 3, 2026. The South Segment started in June 2025 under a $10,225,697.60 contract with Mastec Civil, and in its October 2025 update the city projected full completion in December 2026. Until the city says the South Segment is done, plan on work zones.
Port Royal Road and Buckner Lane intersection
Next up is the intersection where Port Royal Road meets Buckner Lane. The city awarded the job to Adams Contracting for $8,173,903.81, according to the city's project page. Work is set to begin in spring 2027 and take about 12 months. The plan realigns and widens the intersection, replaces the bridge on the west side and adds sidewalks and crosswalks.
Farther up Port Royal Road, the stretch from Saturn Parkway to Kedron Road is in preliminary design, and the city says the board "has not allocated funding for the actual improvements at this time."
US 31 (Main Street)
The widening of US 31, State Route 6, through Spring Hill is in TDOT's statewide 10-Year Project Plan as two projects running side by side. As of the city's page dated December 22, 2023:
| Section | Preliminary engineering | Right-of-way |
|---|---|---|
| Southern portion | 2028 | 2030 |
| Northern portion | 2030 | 2032 |
Construction is planned for 2033, with an estimated total of $299.8 million. Those dates come from TDOT's December 2023 report, and state schedules move. I'll update this when TDOT publishes a newer one.
The long-range road plan
Spring Hill's Major Thoroughfare Plan is dated March 2019, revised January 2021. It lists 32 rows (31 projects plus one marked reserved) in high, medium and low priority. It gives no years and no costs. The five high-priority projects:
| Road | What's planned | Length |
|---|---|---|
| Buckner Lane, Duplex Rd to Thompson's Station Rd | Widen from 2 lanes to 4 or 5 and realign | 2.72 miles |
| Buckner Road Extension, Buckner Ln to Lewisburg Pike | Extend as a 4 to 6 lane road, with the I-65 interchange (now built) | 3.54 miles |
| Kedron Road, US 31 to Saturn Pkwy | Widen from 2 lanes to 3 | 1.28 miles |
| US 31 (Main Street), Miles Johnson Pkwy to Buckner Rd | Widen from 2 lanes to 4 or 5 | 2.18 miles |
| Wall Street, southern end to Miles Johnson Pkwy | Extend as a 2-lane road | 0.61 miles |
The plan's 2040 forecast without improvements has Buckner Lane and that US 31 stretch both at level of service F. An I-65 interchange at Kedron Road is on the plan, at low priority.
The comprehensive plan: Spring Hill Rising 2040
The city's comprehensive plan is Spring Hill Rising 2040, adopted by the board on November 16, 2015. It set "a vision for Spring Hill for the next 25 years." I haven't found a 2025 or 2026 amendment to it.
The plan notes that state law requires that "any land use decision made after the adoption of this plan must be consistent with this plan." It also says a rezoning decision should "not be based solely on the future land use map." Zoning controls what's allowed on a parcel today, and the plan guides what the city approves next.
The plan sorts land into ten character areas. Four of them show the range:
| Character area | What the plan describes | Scale as printed |
|---|---|---|
| Rural Neighborhood | Farms and low-density homes | "Up to one du/two acres" (one home per two acres), more through conservation subdivisions |
| Residential Neighborhood | "low to moderate density" one- and two-story homes | "Moderate density and intensity" |
| City Neighborhood | "compact, walkable urban development" | "Two to four story buildings" |
| Gateway | "the highest intensity of development in Spring Hill" | "Five to 10 story buildings" |
The plan is still in use. On March 9, 2026, staff applied it to a rezoning from agricultural to industrial for the Spring Hill Commerce Center tract on Clark Road, east of I-65, which the plan maps as Gateway. The Planning Commission approved it 6 to 0. Those Clark Road tracts are on the Williamson County side.
Parks and greenways
The city's current parks plan says Spring Hill has about 4 acres of parkland per 1,000 residents, the fewest of its local peers by a wide margin. The city bought Rippavilla in May 2017. A new Parks and Recreation Master Plan is being written now to guide the department for five years, and the city's November 19, 2026 announcement says its public survey is open.
On greenways, the Peter Jenkins Greenway Connector has a $1,417,459.90 Transportation Alternatives grant plus a $294,291.90 city match, approved November 6, 2023. The city says no construction date has been set because final design still needs TDOT's approval.
Annexation and the growth boundary
The city's urban growth boundary on the Williamson County side got bigger. The state's Local Government Planning Advisory Committee certified the expansion on November 11, 2024, and the city's resolution says it was made official on December 20, 2024. In January 2025 the board ratified annexing 19 acres at 0 Clark Road and 25 acres at 2860 Clark Road, in Williamson County, for the Spring Hill Commerce Center.
Annexation here has come at the owner's request in the records I read. In 2025, World Wide Stages asked the city to annex 18.6 acres in Maury County inside the growth boundary, and the Planning Commission recommended it on July 14, 2025. Tennessee law requires the city to adopt a plan of services before it passes an annexation resolution.
What this means if you're buying
Before you write an offer on a Spring Hill home, check these for that address:
- The county. Look at the property's tax record. Williamson or Maury changes which county collects your property tax, and a Spring Hill mailing address doesn't tell you which.
- Sewer, if it's new construction. Ask whether that exact lot has sewer capacity today and whether the city has issued a building permit for it. If it hasn't, ask what happens to your deposit if capacity doesn't come by closing, and get the answer in the contract.
- Planned roads. Look for Buckner Lane work, the Port Royal intersection starting in 2027, US 31 frontage, and any road on the Major Thoroughfare Plan near the street.
An existing home that's already on city sewer is a different purchase from a lot waiting on capacity. I check both kinds of address before my clients write an offer. For the neighborhoods on each side of the county line, see my Spring Hill guide, and for builders, my Spring Hill new construction guide.
Send me the address you're looking at and I'll tell you its county, its sewer status and the planned roads near it. DM me, or text or call 615-392-1186.
Common questions about what's coming to Spring Hill
Is there a sewer moratorium in Spring Hill, TN?
Yes, as of November 2026. A TDEC consent order the city accepted on August 5, 2025 placed a moratorium on new sewer connections for projects without vested sewer rights. Ordinance 25-29, passed January 5, 2026, allocated all remaining plant capacity and says no additional development capacity remains.
When will the Spring Hill sewer moratorium be lifted?
The state decides. Under the consent order, the plant has to go twelve consecutive months without reporting a bypass, or without a sewer overflow over 400 gallons, and TDEC has to rescind or modify the moratorium in writing. No lift date has been announced.
Can I still buy new construction in Spring Hill?
Yes, on lots that have sewer capacity. Ordinance 25-29 named the projects and builders that received allocations, and building permits that were already active kept their capacity. Ask the builder whether your exact lot has capacity and a building permit before you sign.
Is Spring Hill in Williamson County or Maury County?
Both. The city sits in Maury and Williamson counties, and the line runs through town. The property's tax record shows which county a home is in.
What is the Spring Hill sewer line to Columbia?
It's a planned $12 million, 12-inch sewer main from Spring Hill's plant on Mahlon Moore Road to Columbia's system, approved by Spring Hill's board on October 19, 2026. Columbia would take 500,000 to 1.5 million gallons a day once its new treatment plant, due in 2027, and the pump station upgrades are finished.
When will Buckner Lane and US 31 be widened?
Buckner Lane's North Segment is finished, and the South Segment is being widened to five lanes now; the city projected full completion in December 2026. US 31 through Spring Hill is in TDOT's 10-year plan, with construction planned for 2033 as of the city's December 2023 update.
Tell me your price, area and beds, and new listings that fit get sent to you when they come on.
Or call 615-392-1186
Sources
- City of Spring Hill: TDEC consent order and sewer moratorium notice, August 5, 2025
- TDEC Consent Order WPC25-0093 (Resolution 25-183)
- Board of Mayor and Aldermen agenda, January 5, 2026 (Ordinance 25-29)
- City of Spring Hill: interlocal wastewater agreement with Columbia, October 19, 2026
- City of Spring Hill: water and sewer rate notice, May 29, 2026
- City of Spring Hill: Advanced Purification Project
- City of Spring Hill: Buckner Lane Widening
- City of Spring Hill: I-65 and Buckner Road Interchange
- Spring Hill Rising 2040 comprehensive plan
- Spring Hill Major Thoroughfare Plan